General Considerations...
General Statement...
The factors governing design of wastewater treatment facilities are complicated and extensive. Assimilative capacity of
receiving streams, protection of public health, and propagation of fish and wildlife, etc., are taken into consideration
when the State and Federal governments issue a wastewater discharge permit. This permit regulates the quality of the
treated wastewater discharge. In addition to the need for meeting the permissible discharge conditions, the design necessitates compliance with the criteria of being practical and cost-effective. All discharging wastewater treatment facilities are to be designed and constructed to provide at least secondary treatment capable of producing effluent in compliance with Federal and State laws, regulations, and Water Quality Standards. Wastewater collection systems, from the place where wastewater is generated to the place where wastewater is treated, shall be properly designed in accordance
with the projected community growth. Capacities of the systems shall be adequate to accommodate the peak hydraulic demand
and to eliminate hydraulic surge within the system or overflow of wastewater from the system.
Administrative...
All engineer's reports, plans and specifications shall be submitted to this Office and contain the supporting information
for collection systems and wastewater treatment facilities as required by Chapter 10, Recommended Standards for Wastewater Works, 1978 or the latest edition. The standard procedure for submission and processing of such plans and specifications
for review and approval is as follows :
1. Two or more sets of plans and specifications, depending upon funding sources involved, shall be submitted to this Office together with such additional information as may be required for review and approval of the items of sanitary significance. One complete set of approved plans and specifications shall become the property of this Department.
2. Facility plans, design plans, and specifications submitted to the reviewing authority must bear a seal or stamp
of a registered professional engineer, architect or land surveyor licensed to practice within the State of South Dakota.
In addition to these professions, it will be permissible for plumbers licensed to practice within the State of South Dakota to submit plans and specifications for minor projects involving house and community development sewers.
3. Plans and specifications shall be submitted at least thirty days prior to the date from which the owner desires action
by the approving authority.
4. There shall be no deviation from the approved plans and specifications without first submitting revised plans, specifications or addenda to the plans and specifications to the reviewing authority and receiving written supplemental approval. Department approvals become void after two years if construction is not initiated prior to that time.
5. The Department is to be notified when systems or works are to be constructed and placed into service.
6. A complete copy of as-built plans, specifications, addenda and all change orders shall be furnished to the owner.
One complete set shall also be furnished to this Department.
7. All plans shall include information on ownership, lease and/or easement rights, whether permanent or temporary, to the property to be used for projects involving collection systems and treatment plant facilities.
8. A complete copy of the Operation and Maintenance Manual shall be furnished to the owner and to this Department for projects involving mechanical facilities including pumping stations and treatment facilities.
Engineering / Planning...
1. Design Period : In general, wastewater collection systems should be designed for the estimated ultimate contributory population, except in considering parts of the systems that can be readily increased in capacity. A
wastewater collection system should ordinarily be designed to provide for the projected population 20 years hence with a design life of 40 years. A wastewater treatment facility shall ordinarily be designed to provide for the projected
population at least 15 years hence. Whenever cost-effectiveness permits, the construction may be programmed in stages. Similarly, consideration should be given to the maximum anticipated capacity of future institutions, industrial parks, etc.
2. Design Basis : Generally in larger communities having wastewater flows of one (1) MGD or more, a person will generate 100 gallons of wastewater per day containing 0.17 pounds of BOD5. From a hydraulic loading and organic loading standpoint, this represents "One population equivalent (P.E.)." This equivalent population flow, 100 gallons per captia per day (gpcd), is generally accepted as the upper limit for domestic flow projection on a daily average basis
for new wastewater systems serving large communities. Suspended solids (SS) concentrations from domestic flows can be reasonably assumed to contain 0.2 pounds of suspended solids per capita per day. If the use of garbage grinders in a
system is significant, then the design basis should be increased to 0.22 pounds of BOD5 and 0.25 pounds of suspended solids per capita per day. If wastewater flow data are not available, the design average daily flow shall be
based on 75 gpcd for communities with flows less than 1 MGD. An alternate method to determine design capacity could be justified by local water consumption records but shall not be less than 60 gpcd. These records should generally be based
on the average monthly usage for the months of December, January, and February. Special consideration may be needed for communities with highly varying seasonal consumptive water use such as tourism and certain seasonal industrial uses. Projected wastewater flows for a community could be calculated by using 80 percent of the actual water consumption. Allowances shall be made for infiltration, inflow and significant commercial / industrial waste flows which will be
added to the per capita flow rate. If no actual data on infiltration is available, an assumed infiltration design
allowance for existing sewers should be added to the design flow. For existing systems, the minimum infiltration design allowance for the existing sewers and service lines shall be no less than 200 gallons per inch of pipe diameter per mile
of pipe per day. The department recommends that actual flow measurements to determine infiltration rates be conducted for those communities that have collector sewers that lie below the groundwater table.
3. Design Flows :
a. Average Daily Flow : This rate is determined by totaling all of the average flows for existing contributing sources
based on a 24-hour period in which these flows are all generated during dry weather conditions. This rate is generally
used to determine items such as costs, solids loading and organics loading.
b. Minimum Flow : This rate will be based on 50 percent of the average daily flow if flow measurements are not available.
c. Design Average Flow: This rate is determined to be the total of the projected population design domestic flow,
additional maximum design wastewater flow from commercial/industrial plants, existing inflow and groundwater infiltration during wet weather flows.
d. Peak Design : This rate is generally used to determine hydraulic sizing and mass loading of treatment units by
multiplying a factor of 2.0 to 2.5 times the design average flow rate.
e. Peak Hourly Flow : This rate shall be the ratio of peak diurnal flow to daily average flow shall be multiplied times the daily average flow as determined by Figure 1. Use of other values for peak hourly flow will be considered if justified on
the basis of extensive documentation.
The design for various components of the wastewater collection system (collector sewers, interceptor sewers, pumping stations) will be based on peak hourly flow. Force mains from pumping stations will be sized to handle the pumping
capacity of the station.
The design for various components of the treatment plant will be based upon either peak design flow or peak hourly flow. Generally, the organic loading of a wastewater treatment unit is based on the design average flow and the hydraulic loading of a unit is based on the peak design flow. Where recirculation is provided, the recirculation rate shall be added as required.
The design criteria for each flow rate will be designated in the Chapter pertaining to that particular unit or component.
4. New Process or Equipment : Consideration should be given whenever a new process or equipment is involved in the design, documentation of reliability and applicability in full-scale operations is recommended. Consideration should also
be given to the availability of maintenance services or a convenient alternative in the event of mechanical failures. When
an existing treatment works is to be upgraded or expanded, the component parts of the facility should be arranged for convenience of operation and maintenance, flexibility, economy and continuity of equipment.
5. Safety : All mechanical and treatment units should have adequate safety provisions for the personnel concerning occupational health and physical safety.