| - True/False Questions | 1 Point Each |
| 8 Multiple Choice Questions | 2 Points Each |
| 3 Math Problems | 8 Points Each |
| 2 Mandatory Essay Question | 10 Points Each |
| Total Points : 60 | |
| Raw sludge pumping schedule | 7.0 min/30 min |
| Sludge pumping rate | 75 gpm |
| Raw sludge % TS | 4.2% |
| Raw sludge % VS | 73.0% |
| Digester Sludge % VS | 58% |
| Gas Production | 11.5 ft³/day/Lb VS destroyed |
| Percent CO2 (by volume) | 35.5% |
| Other Gases (by volume) | 1.0% |
| Plant flow | 1.8 MGD |
| Specific Gravity of Liq Alum | 1.32 |
| Percent Alum (wt/wt) | 49% |
| Liquid alum | $1.62 per gallon |
| Plant Flow | 4.2 MGD |
| Total Aeration Basin Vol. | 1.55 MG |
| Total Final Clarifier Vol. | 0.60 MG |
| Pri. Effluent BOD | 135 mg/L |
| Pri. Effluent SS | 92 mg/L |
| Final Effluent SS | 22 mg/L |
| MLSS | 3,250 mg/L |
| WAS | 9,100 mg/L |
| Target (Optimum) MCRT | 5.5 days |
| Q | 2.0 mgd |
| MLSS | 2,350 mg/L |
| RAS | 7,350 mg/L |
| SV-30 | 320 mLs/g |
| 1 | D | 2 | B | 3 | C | 4 | B | 5 | E | ||||||||
| 6 | C | 7 | B | 8 | D | 9 | 21,500,000 BTUs/day | 10 | $ 372/day | ||||||||
| 11 | 2.6 lbs/hr.ft2 | ||||||||||||||||