This is a text description of ne-0006a.gif.
The figure shows the evaluating the impact of changes phase for a change plan. The figure shows (from left to right) a change plan, a script and impact report, and a destination database.
On the left is change plan that contains three change requests. An arrow labelled "Generate" points from the change plan to the script and impact report. This means that you generate a script and an impact report from a change plan. An arrow labelled "For" points from the script and impact report to a destination database. This means that the script and impact report is generated for the particular destination database that you have specified.
In summary, from the change plan you generate a script that can be executed at a destination database. When a script is generated for a destination database, an impact report is also generated. The impact report summarizes the number and types of objects that will be modified when the script executes at the destination database.