Skip Headers

Oracle Workflow Developer's Guide
Release 2.6.3.5

Part Number B12161-02
Previous Next       Contents Index Glossary
         Previous  Next          Contents  Index  Glossary

And/Or Activities

In cases where multiple parallel branches transition to a single node, you can decide whether that node should transition forward when any of those parallel branches complete or when all of the parallel branches complete. Use the And activity as the node for several converging branches to ensure that all branches complete before continuing. Use the Or activity as the node for several converging branches to allow the process to continue whenever any one of the branches completes.

And Completes when the activities from all converging branches complete. Calls a PL/SQL procedure named WF_STANDARD.ANDJOIN.
Or Completes when the activities from at least one converging branch complete. Calls a PL/SQL procedure named WF_STANDARD.ORJOIN.


         Previous  Next          Contents  Index  Glossary



Oracle Logo
Copyright © 2003, 2004, Oracle. All rights reserved.