Mechanical and Electrical Design of Pumping Stations - 03...
Chapter - 03 : Design Memorandum Requirements...
3-1. General...
The design memoranda are prepared in the preconstruction
engineering and design (PED) phase of a project.
This phase begins the most intensive engineering effort
and culminates with the preparation of contract plans and
specifications. The design engineer should also be
involved in the reconnaissance and feasibility phases of
the project. The applicable portions of ER 1110-2-1150
will govern the contents and formatting of the various
required submittals. The submittals required for a particular
project will be discussed at the earliest design coordination
meeting, and the listing of design memoranda
required will be established either at this meeting or as
early as possible after this meeting. The following
describes design documents developed during the design
phase of a project. Other design documents, such as
letter reports, can be substituted but should still contain
the information and data required below.
3-2. Design Memoranda and Documents...
For each project, there are different combinations of
design memoranda prepared before proceeding to plans and specifications. These include General Design Memorandum,
Feature Design Memorandum, Letter Reports,
and Design Documents. Station layout and equipment
selection should be investigated in sufficient detail, in the
early design memorandum stage, to permit citing of the
station and preparation of a cost estimate. Hydrology
and hydraulic studies should present the required
pumping conditions used for selection of the pumps.
Information should include discussing the use of Government-
furnished equipment if that method of pumping unit
procurement is proposed. Detailed mechanical and electrical
design data and computations should be included to
allow approval of the final layout and design before
preparation of plans and specifications. The results of
alternative studies for the station layout and equipment
selection should be presented. Design computations to
determine size, strength, rating, adequacy, and interrelationships
of mechanical, electrical, and structural items
should be shown in sufficient detail to allow an engineering
review. All formulas and assumptions used should
be indicated. Copies of typical manufacturers’ performance
data for the proposed equipment and correspondence
with manufacturers should be included. Any
deviations from this manual must be indicated in the text
portion of the memorandum. The memorandum should
include an analysis of the schedules for the procurement
of the pumping equipment and construction of the pumping
station.