Mechanical and Electrical Design of Pumping Stations - 13...
Chapter - 13 : Power Supply...
13-1. General...
When the power requirements for the pumping station
have been tentatively established, the adequacy of the
intended source of electrical power and any limitations of
that source must be determined before proceeding with
station design (Plate 10). The design investigations
should disclose the optimum system operating voltage,
capacities, and location of existing utility facilities which
may be involved in the supply of power to the pumping
station, supply system reliability, voltage regulation,
inrush current limitations, power factor restrictions, and
short circuit characteristics. The Electric Power System
Data Sheet in Appendix G is a convenient means to
organize the information received.
13-2. Station Operating Voltage...
It is extremely important that the proper operating voltage
for the motors be selected, if the minimum overall
installed cost of equipment is to be realized. Most floodcontrol
pump stations operate at either 480 or
4,160 volts. As a general rule-of-thumb, motors of
150 kW (200 HP) and below are usually most economically
operated at 480 volts. Above 150 kW (200 HP),
2,300- or 4,000-volt motors should be considered. Once
the station capacity has been determined, the utility
should be contacted to determine what utilization voltages
are available. The utility rate structure and discounts
such as untransformed service credit must also be
obtained and analyzed. Determination of the most economical
operating voltage requires accurate estimation
and comparison of the complete electrical installation
costs required for each operating voltage considered.
Costs which must be considered include line construction,
substation installation, motors, controls, conduit/
cable sizes, and floor space required.
13-3. Power Supply Reliability and Availability...
( a ) General.
The first step in assuring an adequate
power supply to a pumping station is to define the degree
of reliability needed. This is not an easy task that results
in the assignment of a numerical value. It is, instead, an
evaluation of the tolerable power outages versus the additional
costs to reduce the probability of outages. Some
factors to consider in determining the degree of reliability
needed in the power supply are:
(1) The type of property being protected. Is it cropland,
industrial plants, or urban areas?
(2) The consequences if the pumping station fails to
operate when required. Would an industrial plant be
inundated causing immediate damage or could crops
planted in a rural area tolerate submergence for a short
time? Is ponding available? Would residential areas be
flooded? Could there be potential human injury?
(3) The frequency and duration of outages that are
acceptable to prevent any of the above.
(4) The time of year flooding is likely to occur.
Does that pose any special problems such as overloading
total utility capabilities?
Once the designer has established a feel for the need of
continuity of service, contact with the utility is necessary
to establish a system to meet that need. Several meetings
or correspondences may be required to work out final
details of the system. Chart G-1 of Appendix G is a
flowchart for interfacing with the power company.
( b ) Availability.
Availability could be defined as the
long-term average that the electric service is expected to
be energized. Outage data, given over a 5-year period,
are usually available from the utility. The number of
outages and duration of those outages over the 5-year
period for the substation which will supply the pumping
station can be used to calculate the availability.
( c ) Distribution system alternatives.
Plate 11A
depicts the functional components of a typical electric
power system. The pumping station designer will primarily
be concerned with subtransmission and distribution
systems when discussing reliability considerations
with the utility. Basically, there are two types of distribution
systems:
(1) Radial.
(2) Network.
A radial system has only one simultaneous path of power
flow to the load; a network has more than one simultaneous
path of power flow to the load. A complete listing
of the variations of these two broad groups falls outside
the scope of this document. For an in-depth description
of the various configurations, consult Electric Utility
Engineering Reference Book--Distribution Systems by the
Westinghouse Electric Corporation (1980). Plate 11B indicates some of the more commonly used distribution
system configurations. Beginning at the top left of the
drawing with the network primary feeder, the system’s
reliability increases as one moves clockwise around the
loop. In general, the usage of a radial feed should be
limited to projects where either the economics or characteristics
of the protected property do not justify or require
a more expensive network. Not all of the network
schemes shown will be available from every utility.
Consultation with each utility will be necessary to provide
the appropriate system for the particular application.
13-4. Pumping Station Distribution Substation...
( a ) Layout and design.
Normally the Government
contracts with the local utility to design, construct, operate,
and maintain the power supply to the pump station.
In some cases, the electric utility will ask the Government
to provide the transformer pad as part of the pumping
station contract. In such cases, close coordination
between the utility, the Government, and the contractor
will be necessary to ensure pad sizes, and mounting bolt
locations are as required by the utility’s transformers or
other substation equipment. The substation should be
located as close to the pumping station as possible.
Further guidance on rights-of-way, ownership, operation,
etc., of the transmission line and substation may be found
in TM 5-811-1, Electric Power Supply and Distribution.
( b ) Transformers.
The type of transformer used, i.e.,
whether single-phase or three-phase, should generally be
determined by the availability of replacements from the
local power company stock. Most utilities keep an
inventory of replacement transformers of the various
sizes necessary to provide quick replacement. The
designer should inquire as to the location of transformer
storage and the length of time required to transport and
install it in an emergency. All transformers used must be
non-PCB to comply with all Federal, State, and local
laws. It is common in rural areas to employ three single-phase transformers connected either wye-delta or
delta-delta so that, in the event of a transformer failure,
they can remain in operation when connected in an opendelta
configuration. However, this configuration should
be used with caution since it prohibits the application of
ground fault relaying as well as producing inherent
unbalanced voltages which could result in the overloading
of motors. Another, more attractive, option would be
the furnishing of a fourth single-phase transformer or a
second three-phase transformer as a spare.
13-5. Supply System Characteristics...
An interchange of information between the designer and
the utility is necessary if the pumping station electrical
system is to be compatible with the power supply furnished.
The designer should obtain the data requested in
Appendix G from the local utility supplying power to the
proposed pump station. To prepare the short-circuit
studies indicated in Paragraph 23-3, the designer will
need to obtain the maximum fault current available from
the utility as well as information concerning the distribution
substation transformer impedance. The designer
should transmit station loads and motor starting requirements
to the local utility as soon as they become available
so that the utility can prepare an analysis of the
impact upon their system. The utility can then advise the
designer of power factor and motor inrush current limitations.
After details of the electrical system have been
coordinated, the designer should request time-current
curves of the substation primary side protective devices
so that a coordination study as described in Paragraph
23-2 can be prepared.
13-6. Pumping Station Main Disconnecting Equipment...
For guidance on selection of the pumping station main disconnecting equipment, see Paragraph 15-2.